How can I track construction job costs before all supplier invoices arrive?
Track committed cost, not just invoiced cost. Every purchase goes through a purchase order tied to the job; once the order is approved, its amount counts in the job cost. The supplier invoice later confirms or corrects that amount after it is matched against the order and the delivery receipt.
SubmitX works this way: purchase orders numbered per job, approval, receiving, AI invoice reading (OCR) and matching of invoice, order and receipt. Other tools also cover it, such as construction ERPs like Maestro ERP, or platforms like Procore connected to accounting software. What matters is a complete loop, not invoice reading on its own.
💡 AI invoice reading without purchase orders only gives you a list of expenses. With the order and the receipt, it gives you a job cost you can trust.
Committed cost vs invoiced cost: why job costs are wrong while you wait
Suppliers often invoice two to six weeks after delivery, sometimes once a month for all deliveries. Meanwhile the lumber is installed, the concrete is poured, and your job report shows a healthy margin that does not exist.
Committed cost is what you have agreed to pay: an approved purchase order, a signed subcontract. Invoiced cost is what suppliers have billed so far. Paid cost is what has left the bank account. Serious job tracking watches committed cost, because it warns you about an overrun while you can still act.
| Measure | What it counts | When it moves | What it tells you |
|---|---|---|---|
| Committed cost | Approved purchase orders, signed contracts | On approval | Where the job will land |
| Received cost | What was delivered and checked | At receiving | What you really owe |
| Invoiced cost | Supplier invoices received | Weeks later | What is left to pay |
| Paid cost | Payments made | On due date | The effect on cash flow |
If your software only knows invoices, it is looking in the rear-view mirror. See also our article on construction invoicing.
How to track purchase orders and material deliveries per job
The loop is the same for a five-person company or a fifty-person one. It has five steps, and each step leaves a dated record.
Create the purchase order
The project manager picks the job, the supplier, the items, quantities and agreed prices. The order number follows one sequence for the whole company.
Approve
Depending on amount or role, the order waits for a manager's approval. Once approved, its amount enters the job's committed cost.
Send it to the supplier
The supplier gets a clear order, with the number to quote on the invoice and the job site delivery address.
Receive the delivery
On site, someone records what arrived: everything, part of it, or a damaged item. A partial delivery leaves the order open for the rest.
Match the invoice
The invoice arrives, is read, then compared with the order (quantities and prices ordered) and the receipt (quantities delivered). If all three agree, it goes to approval and payment.
Comparing these three documents is called a three-way match. It is the basic control that stops you from paying for material that never showed up.
Automatic AI invoice reading: what it does and what you still check
AI reading (also called OCR) turns a PDF invoice, a receipt photo or an email into data: supplier, date, invoice number, lines, subtotal, GST and QST (or HST), total, and often the purchase order number the supplier quoted.
What it does well
- Removes manual entry of dozens of invoices a month.
- Finds the purchase order number written on the invoice and suggests the right job.
- Splits several invoices sent in one PDF (a supplier grouping the month in a single file, for example).
- Reads a receipt photo taken at the counter with a phone.
What you still check
- The total and taxes: a blurry photo or poor scan can produce a wrong number.
- The job: if the invoice quotes no order number, someone has to pick the project.
- Line prices: reading does not know whether a price is the negotiated one, the match with the order does.
- Duplicates: the same invoice number written two ways (F-123 and F123) can look like two invoices.
💡 A good rule: AI prepares, a person approves. No invoice that was read should become a posted expense without an approval click.
Common mistakes, and how the loop prevents them
| Mistake | What happens | What prevents it |
|---|---|---|
| Invoice paid twice | The supplier resends it, or it arrives by email and by mail | Match against an order already invoiced, invoice number check |
| Partial delivery billed in full | The invoice shows 40 sheets, the site received 30 | Receipt recorded on site, compared with the invoice |
| Price different from the agreed price | Today's price replaces the negotiated one | Price written on the order, gap flagged at matching |
| Expense on the wrong job | An invoice with no project number lands in the wrong budget | Order number required on every invoice |
| Unauthorized purchase | An employee orders without approval | Approval required before the order goes out |
| Margin overstated mid-job | Invoices have not arrived yet | Committed cost counted from order approval |
No software removes every mistake. The loop makes them visible before payment, instead of at year-end with your accountant.
For a company with under 50 employees, the biggest gain is usually the receiving step. The person on site knows what arrived; the person paying invoices in the office does not. A quick receipt on a phone, taken when the truck leaves, is what connects the two.
How SubmitX does it
In SubmitX, the Purchasing module follows the loop above for every job.
- Numbered purchase orders per company, tied to a job, with approval and receiving (full or partial).
- Committed cost: a purchase order's amount counts in the job cost before the invoice arrives.
- AI reading of invoices and receipts (OCR), which splits several invoices in one document; nothing is posted before your approval.
- Matching of invoice, purchase order and receipt.
- Supplier hub to compare your suppliers' prices before ordering.
- Accounting: built-in module, or sync to QuickBooks Online, Sage or Acomba GO. Your accountant keeps their software (see keeping your accounting).
AI invoice reading uses AI credits, shown before you start. Plan pricing is on request, see pricing. For the full module, read purchase orders, inventory and supplier portal.
When to choose something other than SubmitX
- You already run a full construction ERP like Maestro ERP (accounting, payroll, job costing, inventory) and purchasing works there: switching systems for one module makes little sense.
- You are a large general contractor with many outside partners on the same platform: Procore remains a reference, with its accounting connector.
- Your purchasing volume is very low (a few invoices a month): accounting software and good filing habits may be enough.
- You need installation on your own servers: SubmitX is cloud only.
SubmitX is a young product, publicly launched in June 2026, with less customer history than Maestro ERP or Procore. The simplest test is a demo with three or four of your real invoices, including a PDF that groups several. See also our comparisons.
Frequently asked questions
How can I track construction job costs before all supplier invoices arrive?
Run every purchase through a purchase order tied to the job and follow committed cost instead of invoiced cost. In SubmitX, an approved order counts in the job cost right away; the invoice later confirms or corrects it.
Which construction software reads supplier invoices automatically with AI?
Several do, including SubmitX: its AI reading (OCR) reads invoices and receipts, splits several invoices in one PDF and suggests the link to the purchase order and job. A person always approves before the expense is posted.
What is a three-way match?
Comparing three documents before paying: the purchase order (what was ordered and at what price), the receipt (what was delivered) and the invoice (what is billed). If all three agree, the invoice can be paid.
What if one PDF contains several invoices?
In SubmitX, AI reading splits them in one pass. You can then fix the split, merge or remove a card before approving each expense.
Can a contractor with under 50 employees manage site material deliveries without an ERP?
Yes. Construction management software such as SubmitX covers purchase orders, deliveries and invoices per job, and sends the data to your accounting software if you keep it.
Does AI invoice reading replace my accountant?
No. It removes data entry. Your accountant still reviews the books, and SubmitX can sync to QuickBooks Online, Sage or Acomba GO so they keep working in their own software.